Oracle reportedly sent ‘force majeure’ notice over New Mexico data center

Bloomberg reports Oracle wants to delay payments if Project Jupiter misses its planned 2028 opening—not walk away as the data center’s main tenant.

Joe WeisenthalJW
Shay BoloorSB
Sam KoppelmanSK
11 Sources, 16d ago, first seen 16d ago

TLDR

Bloomberg, citing people familiar with the situation, reports that Oracle sent a force majeure notice to the Blue Owl Capital unit developing Project Jupiter in New Mexico. Those sources said Oracle is seeking to put off payments if the data center fails to come online in 2028 as planned, rather than leave as its main tenant. CNBC reports Oracle shares fell 4% on September 24, 2026, following Bloomberg’s report.

Combined views

1.3M

11 Sources, first seen 16d ago

7K likes231 comments910 saves669 reposts

Combined views

1.3M

11 Sources, first seen 16d ago

7K likes231 comments910 saves669 reposts

Oracle has sent a force-majeure notice to the developer of Project Jupiter, a massive AI data center campus under construction in southern New Mexico, Bloomberg reports, citing people familiar with the situation.

Featured Source

The notice went to a unit of Blue Owl Capital, according to the report. Oracle is seeking protection from payments if the campus does not open in 2028 as planned, CNBC reported. That is narrower than canceling the project or ending Oracle's role as its main tenant. CNBC said Oracle shares fell 4% on Sept. 24 after Bloomberg published the report.

A project already navigating permit fights

Project Jupiter is planned for Doña Ana County near Santa Teresa and is intended to host AI infrastructure for Oracle and OpenAI. Its power plan has changed during development. Oracle said in June that an updated application replaced an earlier gas-turbine and diesel-generator design with a Bloom Energy fuel-cell microgrid.

The new design did not end the project's regulatory uncertainty. In August, the Albuquerque Journal reported that the New Mexico Supreme Court temporarily paused proceedings on a key air-quality permit. The same report said the State Land Office had twice rejected requests to route a gas pipeline across state land.

Those obstacles help explain the financial significance of the reported notice. Force majeure is a contractual mechanism that can excuse or delay obligations when events outside a party's control disrupt performance. Whether Oracle's notice meets that legal standard, and how the developer will respond, remain unresolved in the public reporting.

Sentiment

Positive——Negative

Summary

Not enough discussion yet.

No sentiment analysis available yet.

Sentiment

Positive——Negative

Summary

Not enough discussion yet.

No sentiment analysis available yet.

13 Sources

BloombergOracle Cites ‘Force Majeure’ to Shield Itself on Controversial Data Center16d
CNBCOracle shares drop on report it sent 'force majeure' notice about data center project16d
Joe Weisenthal@TheStalwartWe're starting to see some things *ORACLE SENDS FORCE MAJEURE NOTICE OVER NEW MEXICO DATA CENTER16d
Shay Boloor@StockSavvyShay$ORCL and $BE are both down after Oracle reportedly sent a force majeure notice on its New Mexico data center as power and permitting delays pushed Project Jupiter behind schedule. The $165B campus depends on 2.5GW of Bloom fuel cells making this another example of power and permitting becoming constraint on AI infrastructure.16d
Sam Koppelman@SammyKoppelmanThis was an article worth reading from @hntrbrkmedia: https://hntrbrk.com/investigations/bloom16d
tae kim@firstadopterWeird. It's one thing to do force majeure on a bad hurricane or direct wars, but permits? Bloomberg: "Oracle Corp. is moving to shield itself from racking up expenses on a massive data center being built in New Mexico" Oracle "sent the project’s developer, a unit of Blue Owl Capital Inc., a notice citing force majeure, according to people familiar with the situation." "has hit serious setbacks including the denial of a permit key to its plans for energy resources"16d
Ed Zitron@edzitronView post on X16d
Techmeme@TechmemeSources: Oracle sent a force majeure notice to Blue Owl to delay payments on the 2.45GW Project Jupiter data center in New Mexico if it fails to launch in 2028 (Bloomberg) (Visit Techmeme dot com for the link and full context!)16d
TechCrunch@TechCrunchThe notice would allow Oracle to delay payments should the facility miss its 2028 target to come online. https://spr.ly/6016BGiutg15d
Axios@axiosOracle moves to shield itself from AI buildout risks https://www.axios.com/2026/09/24/oracle-force-majeure-blue-owl-openai?utm_campaign=mrf-utm_source=x&utm_medium=organic_social&utm_campaign=editorial&utm_source=twitter&utm_medium=social&mrfcid=202609246ab536242db635028385f56515d
    • Home
    • Technology
    • Gaming
    • Entertainment
    • World & Business
    • Science
    • Sports
    • AI
    Oracle

    13 Sources

    BloombergOracle Cites ‘Force Majeure’ to Shield Itself on Controversial Data Center16d
    CNBCOracle shares drop on report it sent 'force majeure' notice about data center project16d
    Joe Weisenthal@TheStalwartWe're starting to see some things *ORACLE SENDS FORCE MAJEURE NOTICE OVER NEW MEXICO DATA CENTER16d
    Shay Boloor@StockSavvyShay$ORCL and $BE are both down after Oracle reportedly sent a force majeure notice on its New Mexico data center as power and permitting delays pushed Project Jupiter behind schedule. The $165B campus depends on 2.5GW of Bloom fuel cells making this another example of power and permitting becoming constraint on AI infrastructure.16d
    Sam Koppelman@SammyKoppelmanThis was an article worth reading from @hntrbrkmedia: https://hntrbrk.com/investigations/bloom16d
    tae kim@firstadopterWeird. It's one thing to do force majeure on a bad hurricane or direct wars, but permits? Bloomberg: "Oracle Corp. is moving to shield itself from racking up expenses on a massive data center being built in New Mexico" Oracle "sent the project’s developer, a unit of Blue Owl Capital Inc., a notice citing force majeure, according to people familiar with the situation." "has hit serious setbacks including the denial of a permit key to its plans for energy resources"16d
    Ed Zitron@edzitronView post on X16d
    Techmeme@TechmemeSources: Oracle sent a force majeure notice to Blue Owl to delay payments on the 2.45GW Project Jupiter data center in New Mexico if it fails to launch in 2028 (Bloomberg) (Visit Techmeme dot com for the link and full context!)16d
    TechCrunch@TechCrunchThe notice would allow Oracle to delay payments should the facility miss its 2028 target to come online. https://spr.ly/6016BGiutg15d
    Axios@axiosOracle moves to shield itself from AI buildout risks https://www.axios.com/2026/09/24/oracle-force-majeure-blue-owl-openai?utm_campaign=mrf-utm_source=x&utm_medium=organic_social&utm_campaign=editorial&utm_source=twitter&utm_medium=social&mrfcid=202609246ab536242db635028385f56515d